Overview

Building on State Conservation District land in East Hawaiʻi — even along the scenic Hāmākua Coast — is possible, but it's heavily regulated.
While this guide focuses on the Hāmākua Coast, the overall process and requirements are very similar across the rest of Hawaiʻi.

This is just a summary of the key steps and considerations — there’s a lot more detail behind each part of the process.
If you'd like a deeper breakdown or want to explore options for a specific property, feel free to contact me.


1. State vs. County Jurisdiction

  • State Conservation Land: Managed by the DLNR’s Office of Conservation and Coastal Lands (OCCL).
  • County Role: Even after State approval, County permits are needed for building codes, wastewater systems, and possibly shoreline-related permits.

Key Point: The State controls what can be built; the County controls how it’s built.


2. Conservation Subzones (and Why They Matter)

Hawaiʻi Conservation District land is divided into five subzones:

SubzoneDevelopment OutlookNotes
ProtectiveExtremely restrictedFragile ecosystems, no new homes
LimitedVery restrictedPossible if replacing old use
ResourcePossible, case-by-caseSustainable uses, farming, one home may be allowed
GeneralMost flexibleHomebuilding more feasible (still needs permit)
SpecialHighly customizedBased on unique site designation

Important: Even in Resource or General subzones, nothing is automatic — everything needs DLNR approval.


3. Hāmākua Coast Specific Challenges

  • Steep Terrain: May require expensive engineering to address erosion and stability.
  • Scenic and Cultural Sensitivity: Sites near gulches and beaches are scrutinized for visual impact.
  • Infrastructure: Parcels often lack utilities; off-grid setups (solar, catchment, septic) are typical.
  • Environmental Protections: You may be required to do biological or archaeological studies.

4. Basic Steps to Build

Summary Process:

  1. Confirm Subzone: Use State GIS maps or request OCCL confirmation.
  2. Environmental Assessment (EA): Hire consultants for environmental, cultural, archaeological studies.
  3. Submit a Conservation District Use Application (CDUA): Proposal to DLNR for review.
  4. DLNR Approval: Board of Land and Natural Resources (BLNR) decision.
  5. Obtain County Permits: Building, wastewater, grading, shoreline if needed.

5. Timelines

StageTypical Duration
Environmental Assessment6–12 months
DLNR/CDUA Review6–9 months
County Permits2–6 months

➔ Total: Roughly 18–24 months before construction can start (if everything goes smoothly).


6. Estimated Planning Costs

ItemEstimated Cost
Environmental Assessment & Studies$20,000–$50,000
CDUA Filing Fees$250–$2,500
Architect / Consultant Fees$10,000–$30,000
County Permitting Fees$5,000–$10,000

➔ Rough Total: $35,000–$90,000 before any building begins.


7. Special Notes

  • Second Homes: Conservation zoning usually allows only one residence per parcel. Adding a second home later would be extremely difficult.
  • Short-Term Rentals: Vacation rentals (Airbnb, etc.) are not allowed without a separate and rarely granted permit.
  • Home Design: Must be modest, blend into the environment, and minimize land disturbance.
  • Timeline Enforcement: DLNR permits usually have strict time limits to start and complete work. Delays can cause permits to lapse.

8. Real-World Examples

Here are a few real cases that show what can happen when building (or not building) on Conservation land:

  • ✅ Approved:
    Goehring Residence – Kolekole Beach Park Area (Honomū, Hāmākua Coast)
    A single-family home was approved after a thorough Environmental Assessment and a design that blended into the natural landscape.
    ➔ Read More
  • ❌ Fined:
    Silva Property – Unauthorized Expansion (East Hawaiʻi)
    A property owner expanded a house without DLNR approval and was fined $85,000 after enforcement action.
    ➔ Read More
  • ❌ Denied:
    Gapp Property – Illegal Activities and Subdivision (Puna)
    Unauthorized grading and an illegal subdivision attempt led to enforcement fines and a denial of further land use.
    ➔ Read More
  • ❌ Fined:
    South Kona Vacation Rental – Unauthorized Short-Term Rental
    An unpermitted vacation rental operation in Conservation land resulted in significant fines for the homeowner.
    ➔ Read More

Conclusion

Building on Conservation land along the Hāmākua Coast is possible, but it requires a major commitment to time, cost, and environmental stewardship.
It’s a great fit for buyers who are patient, flexible, and serious about protecting the land — but it’s not a quick or guaranteed process.

As a realtor, setting these expectations early helps buyers make fully informed decisions.


Reference Sources

  • Hawai‘i Administrative Rules Title 13, Chapter 5 (Conservation District Rules)
  • DLNR Office of Conservation and Coastal Lands (OCCL)
  • Hawai‘i County Planning Department
  • State Land Use Commission (LUC) Land Use Maps
  • Hawai‘i Environmental Review Program (Environmental Assessments and Notices)
  • Public BLNR Decision Meetings and Enforcement Cases (Big Island)
  • Hāmākua Coast Community Development Plan
  • Hawai‘i GIS Open Data Portal (Conservation Subzones Layer)

If you are interested in the full 13 page analysis, you can find it here.

About Me

I’m Dan Tousignant, the owner of Cape Project Management Inc. and a Real Estate Broker for Living on Big Island Realty (RB-24565), Through oahumanagement.com, we provide affordable, local registered agent services to businesses across Hawaiʻi. Unlike the big national firms, I keep overhead low and pass those savings on to you, while still making sure you get reliable service and compliance support.